bahrain al dur phase ii project completes the gt21 synchronization
2021-3-6 10:37:31
at 10:57 of march 3, the gt21 of bahrain al dur phase ii project was successfully completed the synchronization with an initial load of 10mw. during the period, the gas turbine, generator, main transformer, plant transformer and other equipment operated normally. the operation of each system was stable and each parameter index was excellent.
to ensure
the smooth synchronization of gt21, basis on the epidemic prevention and
control, the project team made every effort to promote the field commissioning
and successfully completed the commissioning of each subsystem of gas turbine,
crank test, ignition test and other commissioning works. at the same time, the
project team actively strengthened the external communication and coordination,
completed the preparatory work before the synchronization and created good
conditions for the smooth synchronization of the unit.