sepcoiii wins the contract of yuneng yanghuopan project
2021-4-7 18:00:04
on april 6, sepcoiii successfully won the contract of yuneng
yanghuopan integrated coal-power plant section c project.
the project site is located in the south of yanghuopan coal mine
area of yuneng group, dianta town, shenmu city. it is the supporting power
source of ±800kv uhvdc power transmission project between northern shaanxi and
hubei province. it is a key project of shaanxi province.
the project plans to construct 2×660mw ultra-supercritical
coal-fired air-cooled generating units, which are the world's first 660mw
coal-fired air-cooled generating units that adopt natural ventilation and
direct air cooling system. it is a revolution in industrial air-cooling
technology and of great significance to the development of industrial
air-cooling technology. after the completion of the project, it is estimated that the
annual utilization hours will be about 5,500 hours, and the annual electricity
generation will be about 7.2 billion kilowatt-hours, with considerable social
and economic benefits.