new energy company three gorges changyi liutuan wind power project 7.5mw goldwind wind turbine prototype started to be lifted

2023-2-27 17:58:33

on february 25, the first section of the wind turbine tower was slowly lifted by a crane at the wind turbine hoisting site of new energy company’s three gorges changyi liutuan wind power project, marking the official installation of the 7.5mw goldwind wind turbine.

the liutuan wind farm project is located in changyi city, weifang city, shandong province, with a total installed capacity of 50mw and a total investment of more than 80 million rmb. before the start of lifting, the project department scientifically formulated lifting plan, coordinated arrangement of machinery and human resources, carefully check the incoming machinery and lifting apparatus, confirm the construction environment, technical briefing for lifting personnel, at eight o’clock in the morning to start platform installation, panel cabinet installation, afternoon spreader, crane in place, four o’clock in the afternoon to start the first section of the fan tower lifting in place.

at present, the foundation platform of the prototype project has been fully completed, the tower lifting is in full swing, after the tower lifting is completed, the blade lifting and assembly will be carried out.


网站地图