india godda project successfully completes the steam blowing work of unit 2

2023-4-21 8:50:40

at 23:26 on april 19th, the steam blow work of unit 2 of the india godda project is successfully completed, marking the successful completion of another important milestone node of the project.

the steam blow adopts the method of reducing pressure blowpipe and targeting. since the official start of steam blow work on april 10, it is carried out in two stages. control the outlet pressure of the separator to 65~70bar, the outlet temperature of the superheater to 420 ℃~450 ℃, and the blowing coefficient to be greater than 1.2. during the blowing tube, the systems run normally, each parameter indicator is excellent, and the target board spots are qualified which has well received by the owners and ge manufacturers.

in order to ensure the smooth progress of the steam blow work, with the strong leadership of the head office and the strong support of the relevant departments, the project carefully planned and scientifically arranged it, prepared a detailed bleaching plan, and refined the safety control measures. during the steam blow, the project and huafeng weiye technicians personnel work together, and fully which make sure get a high -efficiency results.

the successful completion of the steam blow work has laid a solid foundation for the general start-up of the unit 2.