shaanxi yanchang petroleum fuxian power plant project successfully completes the aerodynamic field test of unit 2

2023-5-10 9:27:29

at 13:00 on may 8, the aerodynamic field test of unit 2 of the fuxian power plant project department of shaanxi yanchang petroleum was successfully completed.

this experiment started on the afternoon of may 3rd, and conducted air volume calibration test, ventilation test, maximum fan output test, power field test, and other tests successively. during the test, the project department carefully organized and reasonably planned, carried out detailed safety and technical disclosure to relevant personnel, arranged day shift and night shift to continuously carry out various tests and measurements 24 hours a day. the personnel of the commissioning, operation, boiler, thermal engineering and electrical teams closely cooperated in the work, strictly followed the test procedures, completed various tests and measurements with high quality, and successfully passed the commissioning, general contracting, supervision acceptance by owners and other units.

the aerodynamic field test is an important test item before boiler ignition, and the successful completion of this test has laid a solid foundation for subsequent boiler ignition blowing and the complete start-up of the unit. 


网站地图